2371
KITCHEN RENOVATION (LABOR)
● Demolition of the kitchen.
● Open Concept: New framing for close existing door- Install LVL- 2 post- Drywall/plaster only in the part where the lvl will be installed and where the existing door will close.
● Install new floor hardwood only in the part where the wall will be removed.
● Open new ventilation for hood Range.
● Install new cabinets including island.
● Install handles for cabinets.
● Install backsplash.
● Carpenters finish: baseboard, casing for 2 windows.
● Install appliances.
● Paint all the kitchen.
PLUMBING
● New water and drain lines.
ELECTRIC
● Does not include any electrical work
MOVING TRASH
PERMITS AND CITY FEES
MASTER BATHROOM RENOVATION
● Demolition all bath (not including ceiling and wall).
● Remove tub.
● Repair wall.
● Repair framing for shower and new framing behind the tub (Schluter Niche).
● Install new drywall and plaster, only in the removed parts.
● Preparation, Schluter system Waterproofing for new shower.
● Installation Tile or Porcelain (Wall and floor only shower).
● Install floor Tile or Porcelain (floor outside the shower).
● Installation (New Vanity, Faucets, Mirror, Bathroom Accessories).
● Carpenters Finish (Install New Baseboard).
● Paint the bathroom.
● Installing glass doors (Includes only installation of regular doors; If you have special measurements and models is requiring a separate estimate).
PLUMBING
● New valve for shower, sink toilet.
● Install new toilet and sink.
● Install new Tub.
ELECTRIC (Change vanity fan and light with new ones).
MOVING TRASH
Any service requested that is not specified has an extra payment.
Thank you; we really appreciate your business.
METHOD OF PAYMENTS.
Down payment 40% $9,000.00 at the day the contract gets signed.
Second Payment 25% $5,625.00 when the work is 50% completed.
Third Payment 25% $5,625.00 when the work is 75% completed.
Final Payment 10% $2,250.00 when work is finished.
MAKE ALL CHECKS PAYABLE TO:
ALEX CONSTRUCTION AND RENOVATION
45 Dan RD, Suite 125, CANTON MA 02021.
CONTRACT TERMS.
Payments must be made by check or cash. **payment must be made within 3 days of project completion, or late fees will be applied. If payment is not made within 30 days of project completion, Alex construction will refer to your account for debt collection. An interest rate of 1.5% a month, or 18% annually will be charged to all past due accounts. A $35,00 fee will apply to any return check. Customers shall be and are responsible for all costs of collection, including reasonable attorney’s fees, arising from any breach of agreement or failure to pay any amount due and owing. This specifically includes, but not limited to, any losses by Alex Construction related to equipment or overhead.
WARRANTY / LIMITATIONS OF LIABILITY
The workman warranty period is 2 years from project completion. Alex Construction warranty covers any defective workmanship performed by the company, as well as any additional warranties imposed by law manufacturer’s warranties for all goods/products used also apply customers exclusive remedy and Alex Construction sole liability under this warranty shall be for Alex Construction to correct any material failure of performance, if such failure is reported to Alex Construction within the warranty period. customers claim for damages shall be limited to the amounts paid for services rendered hereunder only, and shall not include any incidental or consequential damages.
CHANGE ORDERS
Any changes to the scope of work as described above will only be binding and accepted if agreed upon in writing. Payment for a change order is subject to the same terms listed in paragraph 4 of this agreement, except that payment for change order items are not subject to the 50% down payment if the project has already commenced.
In the event of a change order, the parties agree the change order shall become part of this agreement, and subject to all the terms and conditions listed herein.
LEGAL NOTICES
If any portion of provision of this agreement is to any extent declared illegal or unenforceable by a court of competent jurisdiction, then the remainder of this agreement , will not be affected thereby, and each portion and provision of this agreement shall be valid and enforceable to the fullest extent permitted by the law.
This is a Massachusetts contract and shall be trusted and governed in all respects by the laws of the commonwealth of Massachusetts. I hereby accept this scope of work terms and conditions, including payment, and agree that there are no other terms which make up this agreement either expressed or implied.
________________________ ________________________ ________________________ ________________________
Home Owner/ Date Alex Construction Date
Builder Sing and Print and Renovation INC.
Status changed: Pending to Draft.
Status changed: Draft to Pending.
Invoice updated by Alex Marquez.
Status changed: Pending to Paid.
Admin VoidPayment Total: $23,300.00
Status changed: Pending to Paid.
Status changed: Paid to Pending.
Status changed: to Pending.